University / Research Institution
NEC Option A
Specialist Biomedical and Immunology Research
A complex laboratory fit-out bringing several research groups together, with advanced cleanrooms and energy-efficient ventilation.
PROJECT VALUE
£79,000,000
LOCATION
Cambridge, United Kingdom
CONTRACT FORM
NEC Option A
PROJECT DURATION
236 Weeks
LIFECYCLE STAGE
Delivery Controls & Dispute Resolution

Specialist Biomedical and Immunology Research
THE PROJECT IN DETAIL
The Challenge: Where the Programme Was at Risk
A complex fit-out bringing several research groups together, with advanced cleanrooms and specialist ventilation. Progress reports from the trade contractors did not agree with each other, so early delays to the façade and building services went unseen until completion milestones were at risk.
Our Role: What We Did and How It Made a Difference
Introduced lean planning, daily collaborative planning meetings and rolling look-ahead programmes between the structural and building services contractors. When time-related disputes arose during the later fit-out, rebuilt the baseline programme from the project records and carried out time-slice analysis, supported by as-built progress data and written narratives.
THE OUTCOME FOR THE CLIENT
The trades worked to one shared plan, repeated sequencing delays stopped, and all time-related disputes were settled through the NEC contract procedures.