Home / Case Studies
Resort Owner / Operator
AIA Owner–Contractor Agreement
Luxury Hospitality: Post-Storm Resort Recovery
A luxury resort rebuilt after extensive storm damage, with a compressed programme driven by fixed reopening dates.
PROJECT VALUE
$200,000,000+
LOCATION
The Caribbean
CONTRACT FORM
AIA Owner–Contractor Agreement
PROJECT DURATION
Multi-Year Monitoring Appointment
LIFECYCLE STAGE
Delivery Controls & Operational Readiness

Luxury Hospitality: Post-Storm Resort Recovery
THE PROJECT IN DETAIL
The Challenge: Where the Programme Was at Risk
Extensive hurricane damage meant the resort had to be redesigned and rebuilt to fixed reopening dates. Most materials and equipment had to be shipped in, so long supply chains, port delays and limited local resources put the handover dates at risk. Every week counted, as the resort could take no guests until it reopened.
Our Role: What We Did and How It Made a Difference
Provided independent monitoring and assurance, with monthly site visits and 360° photography to check actual progress against each payment application. The live programme fed into executive dashboards, giving the developer and board a clear view of critical path movement.
THE OUTCOME FOR THE CLIENT
Our site checks found an unreported eight-week substructure delay, 12 weeks before it would have hit procurement. The developer re-sequenced the MEP packages, protected the opening date and adjusted payments to match actual progress.
Our view: after a major storm, the schedule has to cover far more than construction. Planning procurement, commissioning and operational readiness from day one is what gets a resort back open on time.
Planning a Similar Development?
Independent assurance at every stage, from appraisal through to completion and beyond.