Neuroscience Research Laboratories, Including High-Containment
A complex neuroscience laboratory over deep basements, built with offsite prefabricated MEP modules and delivered over five years.
PROJECT VALUE
£100,000,000
LOCATION
London, United Kingdom
CONTRACT FORM
NEC Option A
PROJECT DURATION
Five Years
LIFECYCLE STAGE
Delivery Controls & Dispute Resolution

Neuroscience Research Laboratories, Including High-Containment
THE PROJECT IN DETAIL
The Challenge: Where the Programme Was at Risk
A complex neuroscience laboratory over deep basements, built with offsite prefabricated MEP modules. The signature architectural design and complex laboratory services extended the design period. Offsite manufacturing then had to be coordinated with a changing site sequence, and the longer programme led to multiple delay disputes between the parties.
Our Role: What We Did and How It Made a Difference
Built a fully logic-linked master programme and used it to monitor the design and offsite manufacturing timelines, so design release and module production could be tracked against the site sequence. Provided weekly progress reports, milestone payment tracking and visual phasing plans. When claims arose, prepared time-slice delay analyses and as-built programmes to show the causes and effects of each delay.
THE OUTCOME FOR THE CLIENT
Despite an extended programme, multi-million-pound delay claims were settled by agreement, without litigation. Our Founding Director’s planning and delay analysis supported each settlement, and the award-winning centre was delivered.
Our view: on a complex, design-led building, the programme is only as good as the information behind it. Tracking design, offsite and site progress in one place gave everyone the same facts, and that is what allowed the disputes to settle.
Planning a Similar Development?