Asset Owner / Developer
NZS 3910:2013
Commercial High-Rise Development
A prime office building and multi-storey car park in Auckland, where competing extension of time claims under NZS 3910, linked to trade delays and design changes, held up final handover.
PROJECT VALUE
NZ$50,000,000
LOCATION
Auckland, New Zealand
CONTRACT FORM
NZS 3910:2013
PROJECT DURATION
113 Weeks
LIFECYCLE STAGE
Dispute Resolution

Commercial High-Rise Development
THE PROJECT IN DETAIL
The Challenge: Where the Programme Was at Risk
The owner and contractor disagreed over extension of time under NZS 3910. The claims covered cumulative trade delays and structural design changes, and the dispute was holding up final handover.
Our Role: What We Did and How It Made a Difference
Reviewed the contract documents, rebuilt the baseline programme in its native format and tested it against the as-built records. Each proven delay event was modelled in the programme network, and an independent expert report set out the time impact of each event.
THE OUTCOME FOR THE CLIENT
Our analysis gave both parties a clear, shared view of the facts and the time impact of each event. All extension of time claims were then settled by agreement, without formal proceedings.